We have tremendous technical expertise founded on many successful installations of dust extraction systems.
Once the working drawings are approved, our installers are scheduled for the planned site installation times, and any offsite fabrication will be started. Where possible we will select UK equipment supply and fabrication.
Any requirements we may have regarding cranes, electrical work, power etc. will have been confirmed during detailed design, so we will now ensure that these arrangements are in hand on site.
The site programme will have scheduled delivery of the largest kit as late as possible to avoid site issues relating to congestion and storage. We will also ensure we understand local working requirements relating to:
- Working around factory shut downs
- Noise limits
- Out of hours working